Project details

  • Date

     July 16, 2015

  • Client

     Laing O’Rourke Civmec JV

  • Task

     Supply of Structural Steel Conveyor Modules for Conveyor CV1103 and CV104, for the Argyle Underground Expansion.

  • Category

     Fabrication, Surface Treatment, Transport

Project Details

Location: Argyle Diamond Mine

Value: $15M

Date:  April 2008 to February 2009

Client: Laing O’Rourke Civmec JV

Address: Belmont

Contact: Steve Rawlings, Telephone: 08 9477 5670

Project Description:

Laing O’Rourke engaged Dwyer Engineering for the supply of Structural Steel Conveyor Modules for Conveyor CV1103 and CV104, for the Argyle Underground Expansion.

This essentially was 3km of conveyors used to transport iron ore from the mines. Dwyer Engineering were required to supply materials, fabricate, surface treat and load onto provided transport Structural Steel Conveyor Modules including all packers, link plates and attachment brackets, roof attachment brackets, all link plates and packers, Telescopic Ties and all Structural Bolts.

We also supplied Pump Station  No 1 (40 ton), 103/104 Transfer station (40 ton), 104/109 Transfer Station (160 ton), top picture.

The project started with one package of conveyors, but ended up at approximately 45 packages, smaller as larger. The project lasted for approximately one year until Rio Tinto unfortunately cancelled CV103 expansion.